The first uncrewed Gaganyaan mission is unlikely to take off before February 2027. Isro officials said technical fine-tuning and extra simulations caused this delay from the earlier December 2026 plan. "Isro wants to make the mission as foolproof as possible," a senior official said, noting that safety remains the priority.
India's ambitious human spaceflight programme, Gaganyaan, is facing another delay, with the first uncrewed mission now unlikely to take off before February 2027, multiple senior officials within the Indian Space Research Organisation (Isro) have told India Today Digital on condition of anonymity.
The mission was earlier planned for December 2026, but ongoing technical fine-tuning, additional simulations and validation exercises could push the launch beyond the current window.
Officials familiar with the developments at the Human Space Flight Centre (HSFC) and the UR Rao Satellite Centre (URSC) said nearly 80 per cent of the work has been completed, but certain critical activities remain before the spacecraft and launch vehicle can be cleared for flight.
"Isro wants to make the mission as foolproof as possible. This is the first attempt at demonstrating India's human spaceflight capabilities, and there are bound to be uncertainties when technology of this scale is involved," a senior official said.
The officials indicated that the programme is progressing, but the remaining simulations and technical assessments could affect the December launch schedule.
ISRO CHIEF HAD INDICATED DECEMBER LAUNCH
The development comes months after Isro Chairman Dr V Narayanan indicated that the first uncrewed Gaganyaan mission would be among the agency's planned launches for 2026.
Following the successful GSLV-F17 launch carrying EOS-05 in September, Narayanan said six more launches were being planned for the calendar year, including NVS-03 and the first uncrewed Gaganyaan flight.
He underlined the complexity of the mission, revealing that approximately 8,000 tests had been completed. "Unlike other satellite missions, the safety of human life is very important," he said.
Narayanan also said that development of the crew escape system had progressed, while the environmental control and safety system was in advanced stages. The orbital module was undergoing development at the UR Rao Satellite Centre.
GAGANYAAN HAS FACED MULTIPLE TIMELINE REVISIONS
Gaganyaan was originally approved in January 2019 with a target of launching India's first crewed spaceflight by May 2022. The programme initially envisaged two uncrewed missions followed by a crewed flight.
However, the Covid-19 pandemic disrupted hardware production and supply chains, forcing Isro to reassess its timelines. In 2021, the first uncrewed flight was rescheduled for December 2021, with subsequent missions pushed further.
By August 2025, the government was targeting the first uncrewed orbital flight in the fourth quarter of 2025. This was subsequently shifted to the fourth quarter of 2026.
The programme was also expanded in October 2024 from three to eight missions, with three uncrewed flights planned before India's first crewed mission.
WHY THE DELAY MATTERS
The first uncrewed flight, G1, will carry Vyommitra, Isro's half-humanoid robot, to test critical spacecraft systems before astronauts travel aboard.
The mission will validate the human-rated LVM3 launch vehicle, crew module, life-support technologies and recovery systems.
With human lives eventually depending on these systems, Isro is prioritising reliability over launch deadlines. If the latest assessment holds, India's first major step towards sending astronauts into space independently could now come in February 2027.