India’s top infrastructure firms have record order books but face shrinking profit margins. Larsen & Toubro reported order inflows of Rs 1.48 lakh crore in Q2 FY27, yet margins fell. KEC International also saw profits drop. Vimal Kejriwal said, "Executing the order book on time is becoming a problem."

For India's infrastructure companies, winning projects has become the easy part. Executing them profitably is turning into the real test.

Leading engineering, procurement and construction (EPC) companies have record order books that give them revenue visibility for several years. Rising material and logistics costs, labour shortages and execution delays, however, are keeping those orders from turning into better margins and cash flows.

Larsen & Toubro (L&T), the country's largest EPC company, reported record quarterly order inflows of Rs 1.48 lakh crore in Q2 FY27, up 28% year-on-year. That took its order book to Rs 8.54 lakh crore at the end of September. In the same quarter, its Ebitda margin contracted 130 basis points to 8.7% from 10% a year earlier.

L&T is not alone. KEC International's order book reached a record Rs 39,946 crore, but its Ebitda margin fell to 4.96% from 7.07% in the year-ago quarter.

The pressure goes beyond input-cost inflation. Companies are also struggling to complete projects on schedule. KEC's Q2 revenue fell 10.2% year-on-year to Rs 5,468 crore, Ebitda dropped 37% to Rs 271 crore and net profit plunged 81.5% to Rs 30 crore. The company blamed geopolitical disruptions, supply-chain constraints and project execution challenges. It has also cut its FY27 revenue growth guidance to 8-10% from 12-15%, citing revenue deferrals of about Rs 600 crore caused by West Asia disruptions and supply constraints.

"Executing the order book on time is becoming a problem. So that impacts profitability as well as cash flow," Vimal Kejriwal, managing director and CEO of KEC International, told FE. He said transmission and distribution projects are running into right-of-way issues, while labour availability is affecting civil works.

At L&T, part of the margin decline comes from the timing of project execution and revenue recognition. Shankar Raman, president and director-finance, said a smaller share of projects had reached the margin-recognition stage than a year earlier. Under the company's accounting practice, margins are booked only after a project crosses a specified completion threshold. Higher logistics and insurance costs, partly linked to the West Asia situation, have also raised execution expenses. The company expects to seek reimbursement of eligible additional costs from clients under contractual provisions.

Priorities are shifting across the sector. A Tata Projects spokesperson said order availability was no longer the main constraint. The focus has moved to order quality, execution productivity, margin protection and cash conversion. Higher metal prices, longer lead times for transformers and switchgear, and mobilisation delays caused by land availability and approvals are adding to the strain.

Rating agencies expect the pressure to continue even as execution improves. India Ratings and Research (Ind-Ra) has said the sector's biggest challenge is no longer winning orders but converting them into revenue, profits and cash flows. It has named labour shortages, commodity-price volatility, supply-chain disruptions and working-capital constraints as key risks.

Crisil Ratings expects revenue growth at large EPC companies to rise to 9-10% in FY27 from 7-8% in FY26, helped by infrastructure spending and power-sector investment. But Gautam Shahi, senior director at Crisil Ratings, said operating margins are likely to fall 50-70 basis points to 8.2-8.4% because of higher commodity, freight and insurance costs.

A large order book is therefore no longer enough to show that an EPC business is strong. What will decide whether the infrastructure investment cycle delivers lasting returns is whether companies can finish projects on time, recover cost increases and turn revenue into cash.