Jul 30, 2026
✦theage.com.au
Asbestos, dirty soil create headache for key rail loop site
Asbestos and contaminated soil at two Suburban Rail Loop sites are causing delays and cost concerns. On July 31, 2026, sources said conditions at Clarinda and Heatherton were worse than expected. While not dangerous, the strict handling rules for this dirty soil mean the project now faces more time and expense.